![]() |
|
|
|
Focus: Construction June 2008Extensions of time: what discretion does the Superintendent have?In brief: A recent
Supreme Court of Queensland decision has demonstrated how a carefully worded
extension of time clause can give the Superintendent an absolute discretion in
the exercise of their reserve power to grant an extension of time. Partner Nick
Rudge
The factsThe contract in dispute was an amended form of AS2124-1992.1 Hervey Bay (JV) Pty Ltd (the principal) had contracted with Civil Mining and Construction Pty Ltd (the contractor) for construction work at Pialba. The contractor submitted a payment claim of $1,004,708 to which the principal responded with a payment schedule where it proposed only to pay $135,793. The bulk of the amount in dispute was made up of a claim for costs incurred by the contractor because of delay. The contractor submitted an application for adjudication, which resulted in the adjudicator deciding the amount of $921,079 was due and payable by the principal. The principal sought a judicial review that the decision was void as the adjudicator had erred in law by misinterpreting the contract and that the amount payable was $740,000 more. The principal argued that the adjudicator had misconstrued Clause 35.5A and Clause 35.5 B of the contract which stipulated that:
Clause 23 of the contract dealt with the Principal's obligation to ensure that, in the exercise of certain functions, the Superintendent acted honestly and fairly. Clause 23A was then added to emphasise that 'the Principal and Superintendent may exercise those discretions and rights given to them under the Contract in whatever way the Principal or Superintendent decide in their absolute discretion'. The contract also stated that the contractor would not be entitled to an extension of time unless it had strictly complied with the contract and that delay costs were only to be payable where an extension of time for practical completion had been granted. The adjudicator decided that on a proper construction of the contract, the Superintendent should have granted an extension of time and correspondingly should have allowed the delay costs. He found that the contract entitled the Superintendent to allow delay costs absent the grant of an extension of time if the Superintendent concluded that the contractor was entitled to one. He considered the decision in Peninsula Balmain2, where Appeal Justice Hodgson found that the 'power is one capable of being exercised in the interests both of the owner and the builder, and...the Superintendent is obliged to act honestly and impartially in deciding whether to exercise this power'3. Following the Peninsula Balmain decision, the adjudicator concluded that, in considering whether to grant an extension of time under clause 35.5A, the Superintendent was required to act honestly and fairly. Therefore he found that the Superintendent should have granted the extensions under clause 35.5A because that is what an honest and fair Superintendent 'on the balance of probabilities' would have done. The court upheld the submissions of the principal that the adjudicator had misconstrued the contract and that no delay costs were payable. Justice McMurdo found that the adjudicator's interpretation of the contract was inconsistent with the express provision in the clause that the Superintendent was under no obligation to grant an extension of time and also inconsistent with the express provision that the Superintendent's discretion was 'absolute'. Justice McMurdo accepted the correctness of Peninsula Balmain but stated that:
Justice McMurdo found that in the absence of such an obligation there was no entitlement to an extension of time without compliance with clause 35.5 and, as such, the adjudicator was wrong to have included delay costs in the progress payment.
Practical considerationsAlthough criticised, the decision in Peninsula Balmain remains good law in, at least, Victoria, New South Wales and Queensland. In those states, the unamended version of AS2124-1992 will require the Superintendent to exercise the 'reserve' power to grant an extension of time, honestly and impartially, for the benefit of either the contractor or the principal. Extension of time clauses are vital in construction contracts to address when a party's obligations are required to be performed, to defer an entitlement to liquidated damages and, from a principal's point of view, to ensure that the right to liquidated damages is not lost due to the prevention principle. A valid extension of time clause that reserves the Superintendent's discretion to extend time can be drafted in such a way that the Superintendent is not under an obligation to extend time and the discretion remains one that is absolute. Footnotes
For further information, please contact:
|
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
|
|
![]() |
||||